Base Price Indices (as on Reference Index Date preceding Bid Date)
Inflation Factor = ROUND( (CPI×wCPI + WPI×wWPI) ÷ (BaseCPI×wCPI + BaseWPI×wWPI), 2 ). CPI/WPI of the previous month of each IE report date is used.
Change of Scope (COS) & Length Revision
Per requirement: if COS exists, BPC is revised unless a positive COS is paid directly. If project length changes, First Year O&M is revised proportionately by the Length Factor.
Extension of Time (EOT) & CPI/WPI Freeze
If the project is delayed beyond 730 days, EOT is required. When freeze is enabled, the projected O&M inflation factor is frozen at the Second EOT date. Construction milestone CPI/WPI are entered as certified by the division.